A bird’s eye view at Calliope

News
February 18, 2019

Some fantastic footage of Calliope State High School, with construction works now well and truly underway.

An update on site works from Project Manager Dan Burns:

With the preparation of several building pads following Bulk Earthworks activities, footings and inground services have commenced on the first few buildings. Meanwhile, the balance of earthworks are continuing whilst site wide infrastructure (civil stormwater, sewer, etc) will be kicking off shortly.

Follow Paynters for more construction updates throughout 2019 as we deliver this long-awaited project to the CQ region!